After a long, strange year of lockdowns, furloughs and toilet roll shortages, Varlowe's new home is now complete and in operation.
The building has been completely remodelled to house our Fabrication workshop and our new CNC department.
The first floor offices are a modern, comfortable workplace which has room to accommodate new staff as we expand.
It’s been a long time coming, but it’s been well worth the wait.
We are really proud of our company and how it has grown over the years. The new building is a reflection of all the hard work that we put into the industry and the services we provide.
Thank you to everyone who has been involved.
The Building Before
Here is what the building looked like when we first got the keys
February
Knocked through the 1st floor offices
Removed walls in reception area
Removed the central staircase
Divided the workshop into two spaces
Removed old wiring
March & April
Re-enforce first floor space for new staircase
Remodelling of various new workspaces
Start of rewiring
New low level roof for Cnc workshop
Start of the installation of new Ac units
May
Installed new Mezzanine floor on 1st floor for kitchen and extra office space (manufactured and fitted by Varlowe)
Installed new Mezzanine floor for Fabrication storage area and office space (manufactured and fitted by Varlowe)
Plaster Office walls
Paint workshops walls and steel girders
June
Continuing with low level ceiling for Cnc, wiring and Ac
New offices for Cnc workshop (Cad and Inspection Rooms)
New staircase for entry from Fabrication workshop side (manufactured and fitted by Varlowe)
July
Installation of our signature central staircase in reception area which was developed, manufactured and installed by Varlowe (More of the staircase to follow)
New ceiling tiles and lights fitted to 1st floor Offices
August
New signature gates featuring the Varlowe motif installed on both sides of the building. Gates developed, manufactured and installed by Varlowe.
Car Park space has been freshly re-surfaced
September
New staircase for entry to the Fabrication storage area and offices fitted (manufactured and fitted by Varlowe)
Fabrication storage offices finished
Fabrication workshop electrics finished
Low level ceiling and electrics finished in Cnc Workshop
Glass partition for offices overlooking staircase
Floorboards finished in offices
New fire doors fitted throughout
Office kitchen fitted
Workshop canteen fitted
October & November
Cladding started on exterior of building
Handrail and glass fitted to central staircase
New flooring in Fabrication and Cnc workshops
Graphics fitted to glass partition in offices
December
Varlowe Logo fitted to outside of building
Car park space lines painted
Office floor tiles laid
The first two new Cnc machines installed
Start of the 2 week move of office furniture and workshop equipment
January 2020 - We are in!
We are in and fully operational. More pictures to follow as we settle into our new home.